Advanced Wall Framing

Home

Title-24

Emerging Technologies

HVAC

Windows

Insulation & Infiltration

Construction Waste Mgmt

Lighting

Framing

 

 

Some of the techniques described below may not be allowed under some circumstances (i.e., high winds or seismic potential) or in some localities. Be certain to consult local building officials early in the design phase to verify or obtain acceptance of these techniques.

 

WHY USE EFFICIENT FRAMING?

 

 

 

BASIC TECHNIQUES

 

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 


         Figure 1 - Two-Foot Module             Figure 2 - In-Line Framing

 

PLANNING

 

Two-Foot Module - Building on a two-foot module (Figure 1) reduces material use, labor, and waste since many products come in multiples of two feet. For example, with proper planning, the cutoff from a sheet of plywood cut in half can be used in full somewhere else, saving an additional cut and eliminating waste.

 

In-Line Framing - This refers to aligning floor, wall, and roof framing members directly above or below each other, allowing direct downward transfer of loads from one to the next (Figure 2). In-line framing allows elimination of double top plates and is often thought of in the context of 24-inch on-center studs placed directly below roof trusses, which are most commonly placed at 24 inches on-center.

 

Window and Door Layout - Windows with rough openings of 22-1/2” are available. These windows can fit between studs that are on a standard 24” oc layout. Headers can then be eliminated with this method when using in-line framing. For windows or doors wider than the stud spacing, only one extra stud is required if one side of the window or door is placed against a stud which is on the standard layout and metal header hangers are used (Figure 2).

 

Other items - Careful planning of roof length and width (i.e., altering pitch and/or overhang width) can also reduce labor, material use, and waste (consider spacing required for ridge vent - Figure 1). Detailed plans that indicate the presence of each piece of wood, cross bracing, etc. in the house and locations for all other items such as wiring, ducts, and pipes can eliminate conflicts over space, speed installation, and eliminate the need to alter or move studs, joists, etc. later.

 

FRAMING

 

Stud Spacing -In many cases, increasing stud spacing from 16 inches oc to 24 inches oc is structurally acceptable and accepted by codes. The CABO One- and Two-Family Dwelling Code allows the following for studs up to 10 feet long:

 
 

 

 

 

 

 


Lumber plus labor costs for 2x6 @ 24” oc are similar to those for 2x4 @ 16” oc. 2x6 @ 24” oc walls allow more cavity insulation but will require extension jambs (unless drywall returns are used). Also consider 2x4 @ 24” oc walls with foam sheathing when allowed.

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Single Top Plates - If used in conjunction with in-line framing, single top plates are usually acceptable from a structural standpoint, and accepted by model building codes such as CABO and BOCA. These codes require that 3”x 6”, 0.036-inch-thick (20 Ga.) galvanized steel plates be nailed across wood plate joints with three 8d nails at each side (Figure 3).

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Backer

 

Single top plates affect sheathing and drywall needs and installation due to changed wall height. In some areas, 94-1/4” studs (often used for interior walls) are available that allow installation of sheathing and drywall without cutting. Use of 96” studs necessitates cutting to length or adding a strip of drywall at the bottom of the wall. Pre-cut 92-5/8” studs will require “ripping” approximately 1” off the sheathing and drywall. If 94-1/4” studs are not available, using 92-5/8” studs requires the least labor and creates the least waste.

 

Jacks (shoulder studs/cripples)-Jacks can be eliminated when structural headers are eliminated or when metal hangers, such as shown in Figure 7, are used to support structural headers. Elimination of jacks reduces the available nailing area for siding and trim if nailable sheathing (plywood or OSB) is not used - there may be as little as 1-1/2 inches of nailable width next to a window. If needed, a wood backer may be installed behind the sheathing.

 

Outside and Inside Corners -Corners can be framed to decrease lumber use and enable more complete insulation, compared to typical practice (Figures 4 & 5). Attachment of exterior trim and siding at corners should be considered if nailable sheathing is not used. For example, vinyl-siding corners require nailing at a point several inches from the corner. If foam or other non-nailbase sheathing is used, it may be necessary to add a wood nailer behind the sheathing.

 

When drywall clips are used, they should be installed above the level of the interior trim so trim nails will not hit them. The non-coped trim piece should be installed first, against the drywall that bears on the clip, so that the final coped trim piece can be nailed to the stud.

 

Partition Connections to Exterior Walls (T’s) - These are often made by adding studs at each side of the partition, which serve only to attach drywall. In addition to wasting wood, this creates an area that is very hard to insulate. Alternatives include installing “ladder blocks” (Figure 6), drywall clips, or a full length 2x6 or 1x6 behind the first partition stud.

 

Intermediate Blocking - Installing horizontal blocks between studs is generally not required for structural strength or fire/draft stopping in platform framing, at least with standard eight foot high walls.

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Headers -Structural headers are often oversized or installed where not needed, largely for convenience. Properly sizing headers allows better insulation and saves wood. In some cases, single-ply (single 2x6, for example) headers can be used, allowing even better insulation. Headers are not required in non-bearing walls, including most interior walls and gable-end walls with only non-bearing trusses directly above. The following table and accompanying language outlines some header requirements in the 1995 CABO code:

 
 

 

 

 

 

 

 

 

 

 


a Also applies to nominal 4-Inch single headers. Based on No. 2 lumber with 10-foot tributary loads. Not to be used where headers support concentrated loads.

 

b Load-bearing headers are not required in interior or exterior nonbearing walls. Single flat 2-inch-by-4-inch members may be used as headers in interior or exterior nonbearing walls for openings up to 8 feet in width if the vertical distance to the parallel nailing surface above is not more than 24 inches. For such nonbearing headers, no cripples or blocking are required above the header.

 

Insulated headers are possible by using foam sheathing as a spacer in place of plywood or OSB, either between or on one side (preferably exterior) of doubled headers. This is an excellent way to re-use scrap foam sheathing, reducing waste. For assistance in designing headers, consult local structural engineers, code officials, lumber suppliers, or others such as the Western Wood Products Association (WWPA).

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


SHEATHING

 

OSB or plywood sheathing is typically used to provide racking resistance to walls (lateral resistance to wind or seismic loads). Often, some other type of sheathing is used to cover the remainder of the framing. One way to increase the insulating value of a wall is to replace non-insulating sheathing with insulating (foam) sheathing, while still providing racking resistance by one of the following methods:

 

 

Note that the choice of sheathing impacts the ability to nail siding and affects the air leakage and moisture performance of the wall assembly.

 

GRAPHICS

 

All of the graphics for Advanced Wall Framing come from the Building Science Corporation (Boston, MA) and are being used with their permission.

 

FOR MORE INFORMATION

 

NAHB Research Center: sells Cost-Effective Home Building and EEBA Builder’s Guides (series of practical books for various climates). Contact their HOMEBASE SREVICES Hotline: 800-898-2842;

http://www.nahbrc.org; homebase@nahbrc.org

 

Energy Efficient Building Association: P.O. Box 22307, Eagan, MN 55122. 651-994-1536; http://www.eeba.org

 

Southern Pine Council: P.O. Box 641700, Kenner, Louisiana 70064. 504-443-4464;

http://www.southernpine.com

 

Southface Energy Institute: 241 Pine Street, Atlanta, Georgia 30308. 404-872-3549; http://www.southface.org

 

Western Wood Products Association: 522 SW Fifth Ave., Suite 500, Portland, Oregon 97204. 503-224-3930; http://www.wwpa.org

 

Fact Sheet Source

 

The material provided in this fact sheet comes from Appendix J of the National Association of Home Builders Research Center’s “A Guide to Developing Green Builder Programs” and is used with their permission.