Quality Installation of Insulation: Contractor Scope of
Work
Introduction
The purpose of envelope insulation is to provide a
continuous thermal barrier to minimize heat flow through the walls, ceiling and
floor. Insulation serves to keep a home comfortable and reduce costs for
heating and cooling. The home will not be as comfortable and energy costs will
be increased if insufficient insulation is installed, or it is installed
incorrectly, such as being compressed or installed with gaps. Furthermore, it
is not difficult to install insulation correctly. Recent studies have found that over a third of new homes have
lower levels of insulation installed than specified and an additional fifth
have serious installation problems that will result in significantly decreased
effectiveness of the insulation. In addition, virtually all of the homes
studied were found to have numerous insulation installation defects that reduce
the performance of the insulation well below its rated R-value. All of these
problems can lead to defect litigation. These cost-effective procedures will
improve comfort, reduce
energy use, and reduce
potential defect liability exposure.
How to use this Fact
Sheet
The purpose of this
document is to provide the tools to ensure insulation is properly specified and
installed, resulting in a comfortable, energy-efficient home.
Builder: Include these
materials in your bidding and contracting documents. It is meant to form the
basis of a scope of work for both bidding and contracting. Its use will help
ensure consistent bids and quality installations. Attachment I-1 and I-2 are to
be followed by the insulation contractors.
Attachment I-2 is an
installation checklist to be completed by the site superintendent.
Contractor: Follow Attachment
I-1; use Attachment I-2 to check installation quality.
Field Superintendent: Complete Attachment
I-2 to check installation quality and send completed copy to the project
manager or general superintendent.
Criteria for a Quality
Thermal Envelope
Insulation should:
1. Provide a
continuous barrier between the inside conditioned space and the outside,
2. Be installed to the
proper R-value,
3. Be installed
without gaps,
4. Avoid excessive
compression,
5. Be properly labeled
or be proper depth to indicate proper R-value.
Procedures to Install
Insulation for a Quality Thermal Envelope
The following steps
should be followed in the installation of insulation to ensure efficiency and
comfort (for details, see Attachment I-1):
1. Work with the
architect and framer to minimize spaces that are difficult to insulate.
2. Use materials that
meet California quality standards.
3. Install R-values
that meet or exceed design specifications.
4. Install insulation
to completely fill all cavities without gaps and with minimal compression.
5. Account for special
characteristics of the materials used, such as settling, flammability, or water
permeability.
6. Inspect the final job using the
accompanying checklist (Attachment I-2) to ensure a quality installation.
I-1: INSULATION INSTALLATION PROCEDURES
WALL INSULATION
Unfaced batt installation; batts
shall be:
- correctly sized to fit snugly at the sides and
ends
- installed to completely fill the cavity
- cut to fit properly - there should be no gaps,
nor should the insulation be doubled-over or compressed
- non- standard-width cavities shall be filled
by batt insulation cut approximately one inch (1”) wider than the space to
be filled.
- cut to butt-fit around wiring and plumbing, or
be split (de-laminated) so that one layer can fit behind the wiring or
plumbing and one layer fit in front
Faced batt installation, where
used as a vapor barrier: additional instructions:
- facing should be placed toward living spaces
- faced insulation must be properly stapled over
the face of the studs; it must be continuous with no penetrations
- stapling: the batt flange should be stapled to
the face of the framing; flanges from adjacent cavities should overlap per
manufacturers specifications on facing
- each batt should be stapled approximately
every eight (8) inches, or according to manufacturers specifications on
facing
- all tears or breaks in the facing six (6)
inches or longer shall be sealed with duct tape or other waterproof tape.
Tears and breaks in the facing should be minimal.
Narrow-framed cavities and
“chinking”:
- non-standard-width cavities shall be filled by
batt insulation cut approximately one inch (1”) wider than the space to be
filled.
- narrow spaces (2” or less) at windows, between
studs at the building’s corners, and at the intersections of partitions
and walls shall be filled with small pieces of insulation; care should be
taken not to compress the insulation
Special situations:
Installations prior to exterior
sheathing or lath
- all exterior channels (e.g., at wall junctions
and corners) must be filled with insulation
- all exterior walls adjacent to tubs and
showers must be filled with insulation 2.
Obstructions
- insulation shall be cut to fit around wiring
and plumbing without compression
- insulation shall be placed between the
sheathing and the rear of electrical boxes
- insulation shall be cut to fit around junction
boxes
- in cold climates water pipes shall have at
least two thirds of the insulation between the water pipe and the outside.
If the pipe is near the outside, as much insulation as possible shall be
placed behind the pipe and no insulation shall be placed between the pipe
and the inside.
Rim joists
- all rim joists shall be insulated to the same
R-value as the walls
- as necessary, insulation shall be cut to fit
into the rim joist
- an alternative to fitting insulation in a web
truss located at the rim joist is to completely cover the truss with
insulation, snug to the upper and lower floors
Knee walls and Skylight shafts
with framing that will support insulation
- all knee walls and skylight shafts shall be
insulated to a minimum of R-19.
- the insulation shall be installed without gaps
and with minimal compression
- for steel-framed knee-walls and skylight
shafts, external surfaces of steel studs must be covered with batts or
rigid foam unless otherwise specified on the CF-1R and documented by a
form 3R generated by EZFRAME
Knee walls and Skylight shafts
without framing that will support insulation
- for steel-framed knee-walls and skylight
shafts, external surfaces of steel studs must be covered with batts or
rigid foam unless otherwise specified on the CF-1R and documented by a
form 3R generated by EZFRAME
- the house side of the insulation shall be in
contact with the drywall or other wall finish. The attic side shall be
covered with, and supported by a facing rated for attic exposure to stop
air intrusion into the insulation.
HVAC/Plumbing closet
- insulate all walls of interior closets for
HVAC and/or water heating equipment the same R-value as the exterior walls
BATT CEILING INSULATION
Unfaced batt installation:
- batts shall be correctly sized to fit snugly
at the sides and ends
- batts should fill the cavity
- where necessary, batts shall be cut to fit
properly - there should be no gaps, nor should the insulation be
doubled-over or compressed. When batts are cut to fit a non-standard
cavity, they should be cut to be one inch (1”) wider than the cavity.
- batts should be cut to butt-fit around wiring
and plumbing, or be split (de-laminated) so that one layer can fit behind
the wiring or plumbing and one layer fit in front
- for batts that are taller than the trusses,
full-width batts should be used so that they expand to touch each other
over the trusses
- the insulation must cover the wall top plates
- hard covers or draft stops should be placed
over all deep drops and interior wall cavities to keep insulation in place
and stop air movement. If hard covers or draft stops are missing or
incomplete, they should be completed before insulation is completed.
- required ventilation must be maintained: for
eaves or soffit vents, one-inch (1”) of unblocked free air space between
the roof sheathing and the insulation is required.
- where necessary, use baffles to keep the
insulation from blocking the passage of air
- insulation shall cover all IC rated lighting
fixtures
- fixtures that are not IC rated (e.g., halogen
lamps, heat lamps) need to be enclosed in an airtight box that meets fire
codes, and the box covered with insulation. If fixtures are not IC
rated and not enclosed in such a box, they should be replaced or boxed
before insulation is completed.
Faced batt installation, where
used as a vapor barrier: additional instructions:
- facing should be placed toward living spaces
- stapling: the batt flange is stapled to the
face of the framing; flanges from adjacent cavities should overlap
- each batt should be stapled approximately
every eight inches (8”) or per manufacturer’s specifications on the facing
- all tears or breaks in the facing six inches
(6”) or longer shall be sealed with appropriate tape approved by the
insulation manufacturer. Tears and breaks in the facing should be minimal.
Special situations:
Insulation at bridging (cross
bracing)
- batts shall be split lengthwise at the center
and packed half into the lower opening and half into the upper opening of
bridging (cross bracing) of ceiling and/or floor joists
- alternatively, insulation is butted to the
bridging and the space is filled with scrap insulation
Rafter ceilings
- an inch of air space should be maintained
between the insulation and roof sheathing, if necessary to meet local
codes
- facings and insulation should be kept three
inches (3”) away from heated flue pipes or chimneys; follow flue
manufacturer’s recommendations
HVAC platform
- verify that appropriate batt insulation is
placed below any plywood platform or walks for HVAC equipment installation
and access
Attic access
- permanently attach rigid foam or a batt of
insulation to the access cover using adhesive or mechanical fastener
BLOWN-IN CEILING INSULATION
·
baffles must be placed at eaves or soffit vents to keep
insulation from blocking attic ventilation; required ventilation must be
maintained: for eaves or soffit vents, one-inch (1”) of unblocked free air
space between the roof sheathing and the insulation is required.
- hard covers or draft stops must be placed over
all deep drops and interior wall cavities to keep insulation in place and
stop air movement. If hard covers or draft stops are missing or
incomplete, they should be completed before insulation is completed.
- small, inaccessible openings shall be hand
packed with pieces of batt insulation
- attic rulers appropriate to the material
installed must be placed around attic to verify depth: 1 ruler for every
250 square feet, evenly distributed around the attic and clearly readable
from the attic access
- insulation shall be blown to a uniform
thickness throughout the attic, with no high or low spots
- labels from the insulation bags should be cut
out and stapled to a truss vertical near the attic opening
- insulation must go underneath and on both
sides of obstructions such as cross-bracing and wiring
- insulation shall be applied all the way to the
outer edge of the wall top plate
- insulation shall cover IC rated lighting
fixtures
- fixtures that are not IC rated (e.g., heat
lamps) need to be enclosed in a drywall box and the box covered with
insulation. If fixtures are not IC rated and not enclosed in a drywall
box, they should be replaced or boxed before insulation is completed.
- there shall be no excessive compression of
insulation material
- clearances around fossil-fuel appliances and
heat-exhaust vents shall follow local fire protection codes
- no insulation or facing shall be placed in air
spaces surrounding metal chimneys or fireplaces; follow manufacturer’s
recommendations
- batt or rigid foam insulation shall be
installed in areas where blown-in insulation has not been applied, such as
access panels and doors
Special situations:
HVAC platform
- pressure-fill the areas under any plywood
platform or walks for HVAC equipment installation and access or verify
that appropriate batt insulation has been installed
Attic access
- permanently attach rigid foam or a batt of
insulation that is equal or exceeds the R-value of the insulation on the
attic floor to the access cover using adhesive or mechanical fastener
RAISED FLOORS AND FLOORS OVER GARAGES
- batts must be correctly sized to fit snugly at
the sides and ends, but not be so large as to buckle - batts should be no
more than one inch (1”) wider than the cavity
- batts must be cut to fit properly - there
should be no gaps, nor should the insulation be doubled-over or compressed
- batts should fill the cavity
- batts should be cut to butt-fit around wiring
and plumbing, or be split (de-laminated) so that one layer can fit behind
the wiring or plumbing and one layer fit in front
- where there is an air space between the
insulation and flooring, the headers and band-joists must be insulated
- if faced, facing should be placed toward
living spaces
MATERIALS SHALL:
- comply with Uniform Building Code (including
but not limited to 1997 UBC Section 707) and installed to meet all
applicable fire codes
- meet CA Quality Standards for Insulating
Material, Title 24, Chapter 4, Article 3 listed in the California
Department of Consumer Affairs Consumer Guide and Directory of Certified
Insulating Materials
- comply with flame spread rating and smoke
density requirements of Sections 2602 and 707 of the Title 24, Part 2: All
exposed installations must use fire retardant facings which have been
tested and certified not to exceed a flame spread of 25 and a smoke
development rating of 450. Insulation facings that do not touch a ceiling,
wall, or floor surface and faced batts on the undersides of roofs with an
air space between the ceiling and facing are considered exposed
applications.
- be installed according to manufacturer
specifications and instructions
R-VALUE AND U-VALVE SPECIFICATIONS: See CF-1R for minimum
requirements; for non-standard assemblies, also see applicable form 3R.
CERTIFICATES:
A Insulation Certificate (IC-1) signed by the responsible party shall be
provided that states that the installation is consistent with the plans
and specifications for which the
building permit was issued. The certificate shall also state the installing
company name, insulation manufacturer’s name and material
identification, the installed
R-value, and, in applications of blown-in insulation, the minimum installed
weight-per-square-foot consistent with the manufacturer’s labeled
installed-design-density for the desired R-value.
Fact Sheet Source
The material in this fact sheet
was developed by ConSol, Inc. and is public domain.
I-2: INSULATION INSPECTION CHECKLIST
q Insulation Certificate, signed by
responsible party stating:
Manufacturer’s
name
Installed
R-values for Walls, Ceiling and Floors
For
Blown-in insulation: minimum weight per square foot 4.
Walls
q No gaps
q No compression
q Insulation cut around obstructions
3.
q Stapling correct: no gaps, cavity
filled
q External channels, corners, and
areas around tubs and showers insulated
q Small spaces filled
q Rim-joists insulated
Ceiling Batts
q No gaps
q No compression
q Insulation cut around obstructions
q All draft stops in place
q Batts cover trusses
q All top plates covered
q All venting clear: minimum 1”
clearance
q IC rated fixtures covered
q Attic access insulated
Ceiling Blown-in
q All draft stops in place
q All drops covered with hard covers
q
Insulation covers entire surface
q Insulation uniform depth
q Insulation at proper depth -
insulation rulers visible and indicating proper depth
Note:
cellulose insulation settles. Nominal settling for loose fill cellulose is 20%
and for stabilized 5%; installers should either over-blow by these percentages
or to manufacturer’s specifications
q Insulation covering cavities,
drops, scuttles, bracing, and IC rated fixtures
q Insulation covering top plates
q Baffles installed and eaves vents
or soffit vents clear: minimum 1’ clearance 3.
q Bag labels cut out and stapled to
truss vertical near attic access
q Attic access insulated
Floor
q Batts snug but not compressed or
buckled
q All spaces insulated
q If web trusses, rim joists
insulated