Quality Installation of Insulation: Contractor Scope of Work

Home

Insulation and Infiltration

 

 

Introduction

 

The purpose of envelope insulation is to provide a continuous thermal barrier to minimize heat flow through the walls, ceiling and floor. Insulation serves to keep a home comfortable and reduce costs for heating and cooling. The home will not be as comfortable and energy costs will be increased if insufficient insulation is installed, or it is installed incorrectly, such as being compressed or installed with gaps. Furthermore, it is not difficult to install insulation correctly.  Recent studies have found that over a third of new homes have lower levels of insulation installed than specified and an additional fifth have serious installation problems that will result in significantly decreased effectiveness of the insulation. In addition, virtually all of the homes studied were found to have numerous insulation installation defects that reduce the performance of the insulation well below its rated R-value. All of these problems can lead to defect litigation. These cost-effective procedures will improve comfort, reduce

energy use, and reduce potential defect liability exposure.

 

How to use this Fact Sheet

 

The purpose of this document is to provide the tools to ensure insulation is properly specified and installed, resulting in a comfortable, energy-efficient home.

Builder: Include these materials in your bidding and contracting documents. It is meant to form the basis of a scope of work for both bidding and contracting. Its use will help ensure consistent bids and quality installations. Attachment I-1 and I-2 are to be followed by the insulation contractors.

 

Attachment I-2 is an installation checklist to be completed by the site superintendent.

Contractor: Follow Attachment I-1; use Attachment I-2 to check installation quality.

Field Superintendent: Complete Attachment I-2 to check installation quality and send completed copy to the project manager or general superintendent.

 

Criteria for a Quality Thermal Envelope

 

Insulation should:

1. Provide a continuous barrier between the inside conditioned space and the outside,

2. Be installed to the proper R-value,

3. Be installed without gaps,

4. Avoid excessive compression,

5. Be properly labeled or be proper depth to indicate proper R-value.

 

Procedures to Install Insulation for a Quality Thermal Envelope

 

The following steps should be followed in the installation of insulation to ensure efficiency and comfort (for details, see Attachment I-1):

1. Work with the architect and framer to minimize spaces that are difficult to insulate.

2. Use materials that meet California quality standards.

3. Install R-values that meet or exceed design specifications.

4. Install insulation to completely fill all cavities without gaps and with minimal compression.

5. Account for special characteristics of the materials used, such as settling, flammability, or water permeability.

6. Inspect the final job using the accompanying checklist (Attachment I-2) to ensure a quality installation.

 

I-1: INSULATION INSTALLATION PROCEDURES

 

WALL INSULATION

 

Unfaced batt installation; batts shall be:

 

 

Faced batt installation, where used as a vapor barrier: additional instructions:

 

 

Narrow-framed cavities and “chinking”:

 

 

Special situations:

Installations prior to exterior sheathing or lath

 

 

 

Obstructions

 

 

Rim joists

 

 

Knee walls and Skylight shafts with framing that will support insulation

 

 

Knee walls and Skylight shafts without framing that will support insulation

 

 

HVAC/Plumbing closet

 

 

BATT CEILING INSULATION

 

Unfaced batt installation:

 

 

 

 

Faced batt installation, where used as a vapor barrier: additional instructions:

 

 

Special situations:

Insulation at bridging (cross bracing)

 

 

Rafter ceilings

HVAC platform

 

Attic access

 

BLOWN-IN CEILING INSULATION

 

·         baffles must be placed at eaves or soffit vents to keep insulation from blocking attic ventilation; required ventilation must be maintained: for eaves or soffit vents, one-inch (1”) of unblocked free air space between the roof sheathing and the insulation is required.

 

Special situations:

HVAC platform

 

Attic access

 

 

 

RAISED FLOORS AND FLOORS OVER GARAGES

 

MATERIALS SHALL:

 

R-VALUE AND U-VALVE SPECIFICATIONS: See CF-1R for minimum requirements; for non-standard assemblies, also see applicable form 3R.

 

CERTIFICATES:  A Insulation Certificate (IC-1) signed by the responsible party shall be provided that states that the installation is consistent with the plans and  specifications for which the building permit was issued. The certificate shall also state the installing company name, insulation manufacturer’s name and material

identification, the installed R-value, and, in applications of blown-in insulation, the minimum installed weight-per-square-foot consistent with the manufacturer’s labeled installed-design-density for the desired R-value.

 

Fact Sheet Source

The material in this fact sheet was developed by ConSol, Inc. and is public domain.

 

 

 

 

 

 

 

I-2: INSULATION INSPECTION CHECKLIST

 

q       Insulation Certificate, signed by responsible party stating:

Manufacturer’s name

Installed R-values for Walls, Ceiling and Floors

For Blown-in insulation: minimum weight per square foot 4.

 

Walls

q       No gaps

q       No compression

q       Insulation cut around obstructions 3.

q       Stapling correct: no gaps, cavity filled

q       External channels, corners, and areas around tubs and showers insulated

q       Small spaces filled

q       Rim-joists insulated

 

Ceiling Batts

q       No gaps

q       No compression

q       Insulation cut around obstructions

q       All draft stops in place

q       Batts cover trusses

q       All top plates covered

q       All venting clear: minimum 1” clearance

q       IC rated fixtures covered

q       Attic access insulated


Ceiling Blown-in

q       All draft stops in place

q       All drops covered with hard covers

q       Insulation covers entire surface

q       Insulation uniform depth

q       Insulation at proper depth - insulation rulers visible and indicating proper depth

Note: cellulose insulation settles. Nominal settling for loose fill cellulose is 20% and for stabilized 5%; installers should either over-blow by these percentages or to manufacturer’s specifications

q       Insulation covering cavities, drops, scuttles, bracing, and IC rated fixtures

q       Insulation covering top plates

q       Baffles installed and eaves vents or soffit vents clear: minimum 1’ clearance 3.

q       Bag labels cut out and stapled to truss vertical near attic access

q       Attic access insulated

 

Floor

q       Batts snug but not compressed or buckled

q       All spaces insulated

q       If web trusses, rim joists insulated