Riverside 1

  • Test Segment Start Location, Nearest Cross Streets: Van Buren Boulevard and Equestrian Drive
  • Test Segment End Location, Nearest Cross-Streets: Cleveland Avenue and McAllister Street
  • Projected Start Date: July 23, 2013
  • Test Date: August 10, 2013
  • Project End Date: August 24, 2013
  • Test Results: No leak noted
  • Traffic Control Measures: Cleveland Avenue closed in both directions between McAllister Street and John Street
 
Traffic Impact Map

 

Test Site Locations