Inglewood - Crenshaw Boulevard

  • Replacement Segment Start Location, Nearest Cross Streets: On Crenshaw and 104th Street
  • Replacement Segment End Location, Nearest Cross Streets: 8th Avenue and W. 79th Street
  • Replacement Segment Length: 15,145 feet
  • Projected Start Date: Late September, 2014
  • Projected End Date: Mid-December, 2014
  • Traffic Impacts: The excavation and pipeline installation work will be conducted in a series of sections starting on Crenshaw Boulevard at 104th Street. One work crew is expected to advance its sections to the north while a second work crew advances to the south. While each section on Crenshaw Boulevard is being worked on, at least one northbound lane will be closed for the length of the section, plus a safe distance before and beyond the section. While each section on 8th Avenue is being worked on, the southbound lane will be closed for the length of the section. Lane reductions and closures will be in effect Monday through Saturday during work hours and marked with traffic cones and signs. Work hours will be 8 a.m. to 4 p.m., Monday through Saturday.
 

Activity area for the Inglewood-Crenshaw Boulevard Pipeline Replacement

 

Traffic Impact Map of a sample active section on Crenshaw Boulevard