Compton (Active) - Valve Upgrade/Replacement

  • Work Location: Intersection of South Central Ave and East 142nd Street
  • Work Hours: Monday through Friday, 7:00 a.m. – 5:30 p.m.
  • Project Start Date: March 14, 2016
  • Projected End DateJune 10, 2016
  • Traffic Impact: Lane closures will be required and will be in effect during the work hours noted above. These closures, and other traffic control devices, will be marked with traffic signs and cones.
  • What to expect: The valve upgrade involves the installation of two 4’ cabinets and a 20’ antenna pole to enable remote communications with the valve. The cabinets and the antenna pole will be installed at the north east portion of South Central Ave (adjacent to the sidewalk).