Sylmar - San Fernando Road - Active - Replacement

  • Work Location: Construction will take place along San Fernando Road in Sylmar.
  • Work Hours: Monday through Friday, 8 p.m. to 5 a.m. (Subject to permit conditions & City approvals).
  • Project Start Date: August, 2016
  • Projected End Date: January, 2017
  • Traffic Impact: Traffic will be reduced to one lane in each direction on San Fernando Road from south of Sierra Highway to Balboa Boulevard during the work hours noted above.
  • What to expect;: The pipeline replacement work involves installing new pipeline parallel to the path of the existing pipeline. Next, the existing pipeline is taken out of service and all natural gas is safely removed from it. The new pipeline section is then connected to the distribution system and brought into service.