Lompoc - Highway 1 - Active - Replacement

  • Work Location: Highway 1 between George Miller Drive.
  • Work Hours: 
    • Monday - Thursday, 9:00 a.m. - 4:00 p.m. and 8:00 p.m. - 6:00 a.m.
    • Friday, 9:00 a.m. - 2:00 p.m.
  • Project Start Date: July 2017
  • Projected End DateOctober 2017
  • Traffic Control Measures: Lane reductions on Highway 1 during work hours.
  • What to expect: The pipeline replacement work involves installing new pipeline parallel to the path of the existing pipeline. Next, the existing pipeline is taken out of service and all natural gas is safely removed from it. The new pipeline section is then connected to the distribution system and brought into service.