San Fernando Valley - Sepulveda Dam - Active - Replacement

  • Work Location: Near Sepulveda Dam.
  • Work Hours: 
    • Monday – Friday, 7:00 a.m. - 5:00 p.m.
  • Project Start Date: June 2017
  • Projected End DateSeptember 2017
  • What to expect: The pipeline replacement work involves installing new pipeline parallel to the path of the existing pipeline. Next, the existing pipeline is taken out of service and all natural gas is safely removed from it. The new pipeline section is then connected to the distribution system and brought into service.