Torrance - Crenshaw and 190th - Active - Replacement

  • Work Location: Intersection of Crenshaw Place and 190th Street.
  • Work Hours: 
    • Monday - Friday, 10:00 p.m. – 6:00 a.m.
    • Saturday - Sunday, 8:00 p.m. – 8::00 a.m.
  • Project Start Date: April 17, 2017
  • Projected End DateJuly 2017
  • Traffic Impact:  Westbound and Eastbound Traffic along 190th Street will be reduced during various phases of the project. Crenshaw Place will be completely closed during later phase of the project.
  • What to expect: The pipeline replacement work involves installing new pipeline parallel to the path of the existing pipeline. Next, the existing pipeline is taken out of service and all natural gas is safely removed from it. The new pipeline section is then connected to the distribution system and brought into service.