Ventura - Telephone and S. Mills - Pipeline Replacement

There are two pipeline enhancement projects planned for the City of Ventura. If you have any questions, please contact us:
 

Project Call Number:  Olga Quinones, (805) 551-9027
Project Email: Projectinfo@semprautilities.com

Project Area 1: Telephone Road

Project Status: The project is complete.

Project Area 2: S. Mills Road

Project Status: Currently in construction preplanning phase.

Project Details:
 
  • Replacement Segment Start and End Location, Nearest Cross Streets: Telegraph Road and S Mills Road.
  • Projected Start Date: June 2019
  • Projected End Date: December 2019
  • Traffic Impacts: To minimize the impact to the community, work is planned for nights starting at 10 p.m. to 6 a.m.
People passing by a work sites may see an excavation, equipment, vehicles and traffic control signage. The community may also hear some work-related noise and notice an occasional natural gas odor.