Ventura - Telephone Road - Active - Pipeline Replacement

Project Status 1/18: SoCalGas has continued working within our traffic control to locate any underground utilities along our proposed alignment. Traffic control is being staged around the work areas, as we move down Telephone Road. Current day work areas are located east of S Saticoy Avenue and west of S Hill Road. Crews have been excavating, lowering pipe, and plating between S. Saticoy Avenue and S. Wells Road. Current night work areas are located between County Square Drive and Lark Avenue. Excavation work continues east of Gateway Plaza down Telephone Road. Following excavation work, crews have been backfilling and paving as we move down Telephone Road. excavating, lowering pipe, and plating along our proposed alignment. The project is currently at 63 percent completion.

 

Project Call Number:  Nick Brook (805) 551-9027
Project Email: Projectinfo@semprautilities.com

Project Details

  • Replacement Segment Start and End Location, Nearest Cross Streets: Telephone Road between 101 Freeway and Wells Road.
  • Projected Start Date: July 2018
  • Projected End Date: March 2019
  • Traffic Impacts: Eastbound traffic on Telephone Road will be reduced to one lane in and around the construction area. Lane reductions will be in effect during work hours only, Monday through Friday from 9 a.m. to 4 p.m., in the day work areas and 9 p.m. to 6 a.m. in the night work areas. The area will be marked with traffic cones and signs.
People passing by a work site may see an excavation, equipment, vehicles and traffic control signage. The nearby community may also hear some work-related noise and notice an occasional natural gas odor.