Garfield Avenue Pressure Test and Valve Relocation

  • Test North End Location: Garfield Avenue just south of Callita Place

  • Test South End Location: Near Marengo Avenue and Mission Road

  • Valve Location: Intersection of Garfield Avenue and Huntington Drive

  • Projected Start Date: September, 2016

  • Test Date: Wednesday, October 19, 2016

  • Test Result: No Leak Noted

  • Projected End Date: November, 2016

  • Work Hours:

    • Alhambra - 7 a.m. to 4 p.m. - Monday through Friday

    • San Marino - 9 a.m. to 4 p.m. - Monday through Friday

    • South Pasadena - 9 a.m. to 4 p.m. - Monday through Friday

  • Traffic Impacts: For the duration of the testing and relocation operations, traffic control measures will be in place to facilitate the flow of traffic along Mission Road at Marengo Avenue, Huntington Drive at Garfield Avenue, and Garfield Avenue near Callita Place. Motorists are asked to follow all traffic signs and markers for their safety and the safety of others.