Riverside County - West of the intersection of the I-10 Freeway and Haugen-Lehmann Way in Whitewater and ending just east of the intersection of North Hathaway St. & Morongo Rd. in Banning.
Pipeline Testing 3/13/2023 – 9/2023
Work hours: Monday – Friday from 7 a.m. to 5 p.m.
Community impacts: There will be a temporary road crossing and ramp along Rushmore Ave and at the intersection of Morongo Rd. and N. Hathaway St.

Hesperia - On Silverwood St. between Foley Rd. and Perch Place  
Hydrotesting 2/27/2023 – 5/2023
Work hours: Monday – Friday from 7 a.m. to 5 p.m.
Community impacts: No traffic control is required. 

West Los Angeles – at Sepulveda Blvd and Constitution Ave, in front of the Los Angeles National Cemetery Actuator and vault installation 9/26/2022 – 4/2023 Work hours: Monday – Friday from 9 p.m. to 6 a.m. Community impacts: Northbound traffic on Sepulveda Blvd will be reduced to one lane near the construction site during work hours.