Construction Activities by City

Locate the pipeline safety enhancement projects in your area.

Current Activities

Dates provided are estimates, weather and other factors affecting safe working conditions could change the schedules. The public may see trucks and heavy equipment from SoCalGas and our contractors around the general construction areas.

Cactus City & Whitewater

Service roads west of the Cactus City Rest Area exit and along the railway at Tamarack Rd near Cottonwood Rd. 

  • Pipeline Inspection: 5/20/2024 – 8/2024
  • Work Hours: Monday – Friday from 6:00 am to 5:00 pm
  • Community Impacts: Potential Lane closures. 

Diamond Bar

Near intersection of Brea Canyon Rd and Sapphire Ln

  • Temporary Equipment Installation: 6/3/2024 – 7/19/2024
  • Work Hours: Monday – Friday from 7:00 am to 5:30 pm
  • Community Impacts: Traffic control signage, flag personnel, no parking signage, lane closures and detours will be posted along the construction route.

Fullerton

Near Intersection of Highland Ave and Valencia Ave

  • CCM Equipment Upgrades: 7/17/24 - 10/17/24
  • Work Hours: Monday - Friday from 7:00 am to 4:00 pm
  • Community Impacts: Traffic control will be effect for duration of the project.

Glendora

N Valley Center Ave

  • Main and Service Line Replacements: 7/2/24 - 11/12/24
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Lanes in both directions of N Valley Center Ave will remain open but lanes will be narrowed during work hours.  

Homeland & Menifee

Along Briggs Rd and Watson Rd in Menifee and along Highway 74 near Juniper Flats Rd and Naumann Ave in Homeland

  • Direct Examination: 7/8/24 - 11/8/24
  • Work Hours: Monday - Friday from 8:00 am to 4:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and potential detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Inglewood

Near intersection of W 104th St and Crenshaw Blvd 

  • Robo In-line Inspection: 7/8/24 - 8/5/24
  • Work Hours: Monday - Friday from 8:30 am to 5:00 pm
  • Community Impacts: “No Parking” signage will be posted along the construction route.

La Puente

La Puente Station

  • Pipeline Inspection: 6/3/2024 – 09/27/2024
  • Work Hours: Monday – Friday from 9:00 am to 3:30 pm
  • Community Impacts: Traffic control signage, flag personnel, no parking signage, lane closures and detours will be posted along the construction route.

Between Santa Ana River to Puente Station in Riverside and La Puente

  • Tool Run: 6/24/24 - 10/24/24
  • Work Hours: Monday - Friday from 9:00 am to 3:30 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and potential detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

La Quinta

Near Coachella Dr and Anselmo Ave

  • Pipeline Replacement: 6/24/2024 – 09/13/2024
  • Work Hours: Monday – Friday from 6:00 am to 5 pm
  • Community Impacts: Traffic control signage, flag personnel, no parking signage, lane closures and detours will be posted along the construction route.

Los Angeles

Intersection of Lincoln Ave and N Ave 45

  • Pipeline Replacement: 7/8/24 - 8/12/24
  • Work Hours: Monday - Friday from 9:00 am to 3:30 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. Full closure of Lincoln Ave spanning 150 ft from Ave 45. There will also be a closure on Ave 45 from and including the northbound sidewalk up to 12-16 ft away from the west curb. Closure on Ave 45 will span 120 ft centered on Lincoln Ave. A flagger will be present at the intersection of Lincoln Ave and Ave 45 to direct traffic and assist pedestrians. York Blvd and Toland Way will remain open to allow traffic from Lincoln Ave.

Montecito

West of Intersection of Park Ln and Mariposa Ln

  • Valve Automation: 7/8/24 - 9/8/24
  • Work Hours: Monday - Thursday from 7:00 am to 4:30 pm
  • Community Impacts: A lane closure will be in effect along Park Ln's westbound lane approximately 0.48 miles west of Mariposa Ln. Vehicular traffic heading westbound will still be allowed to travel past the construction site with a brief delay, allowing construction to make it safe to proceed. Access to all driveways and trailheads will remain accessible. Traffic control signage, flagging personnel, no parking signage, and lane closures will be posted along the construction route.

Murietta

Los Alamos Rd. between Adams Ave & Hancock Ave

  • Pipeline Inspection: 6/3/2024 – 8/23/2024
  • Work Hours: Monday – Friday from 7:00 am to 4:00 pm
  • Community Impacts: Traffic control signage, flag personnel, no parking signage, lane closures and detours will be posted along the construction route.

Palm Desert

Within Palm Desert Resort Country Club

  • Main and Service Line Replacements: 7/1/24 - 10/31/24
  • Work Hours: Monday - Friday from 7:00 am to 7:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and potential detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Palm Springs

Along E Vista China and Gene Autry Trail

  • Robotic Inspection: 6/3/2024 - 9/3/2024
  • Work Hours: Monday - Thursday from 9:00 am to 1:00 pm
  • Community Impacts: Traffic will be reduced to one lane northbound on N Gene Autry Trail. Traffic will be reduced to one lane westbound on Vista Chino between Gene Autry and N Whitewater Club Dr. Traffic will be reduced to one lane Eastbound on Vista Chino between Volturno Drive and N Via Negocio. Traffic will be reduced to one lane Eastbound on Vista Chino between Sharon Drive and Parkview Drive.

Rancho Mirage 

Near Sunrise Dr & La Ronda Dr

  • Pipeline Replacement: 6/3/2024 – 9/13/2024
  • Work Hours: Monday – Friday from 7:00 am to 6:00 pm
  • Community Impacts: Traffic control signage, flag personnel, no parking signage, lane closures and detours will be posted along the construction route.

Riverside County

West of Desert Center at Hayfield Station to East of Cactus City Station

  • Hydrotest: 7/8/24 - 11/8/24
  • Work Hours: Monday - Saturday from 6:00 am to 4:30 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

San Bernardino

Along State St, north of College Ave

  • Limiting Station Replacement: 6/3/24 - 8/3/24
  • Work Hours: Monday - Friday from 7:00 am to 4:00 pm
  • Community Impacts: Traffic control will be effect for duration of the project.

Near Sycamore Creek Dr and Wildrye Dr

  • Hydrotest: 6/3/24 - 9/3/24
  • Work Hours: Monday - Friday from 7:00 am to 4:30 pm
  • Community Impacts: There will be no parking on Wildrye Drive, just south of Sycamore Creek Drive. Temporary closure of entry and exit at Wildrye Drive and Sycamore Creek Drive will be in effect during construction.

Santa Clarita

Near Intersection of Newhall Ranch Rd and Bouquet Canyon Rd

  • CCM Remote Monitoring Equipment Installation: 7/8/24 - 8/2/24
  • Work Hours: Monday - Friday from 8:00 am to 3:30 pm
  • Community Impacts: One lane eastbound on Newhall Ranch Road will be closed during construction. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Santa Maria

Along Betteravia, between S Oakley Ave and Black Rd

  • Robo In-line Inspection: 7/1/24 - 10/31/24
  • Work Hours: Monday - Friday from 7:00 am to 6:00 pm
  • Community Impacts: None. Traffic control signage, flag personnel, and no parking signage will be posted along the construction route.

Somis

North of Intersection of La Vista Ave and W Los Angeles Ave

  • Robo In-line Inspection: 7/8/24 - 12/8/24
  • Work Hours: Monday - Friday from 7:00 am to 4:30 pm
  • Community Impacts: No traffic impacts are anticipated to occur during construction activities.

Taft

Next to Lake Station Rd

  • Valve Remediation: 7/1/24 - 7/29/24
  • Work Hours: Monday - Friday from 7:00 am to 4:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Tulare

17297 Road 96

  • Compressor Installation: 6/24/24 - 8/12/24
  • Work Hours: Monday - Friday from 6;30 am to 4:30 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Ventura

Near intersection of N Olive St and W McFarlane Dr

  • Hydrotest: 6/3/24 - 9/3/24
  • Work Hours: Monday - Saturday from 7:00 am to 5:30 pm
  • Community Impacts: None

Ventura County

Near intersection of Sycamore Dr and N Ventura Ave

  • In-line Inspection: 6/3/24 - 8/12/24
  • Work hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flag personnel, and no parking signage will be posted along the construction route. Lane closures will be in effect for all lanes along Sycamore Dr. Access will remain available to first responders and residents in the area with brief delays.

Visalia

31287 Road 68

  • Compressor Installation: 6/24/24 - 8/12/24
  • Work Hours: Monday - Friday from 6;30 am to 4:30 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Yorba Linda

Along Esperanza Road, throughout Yorba Linda, ending near China Hills State Park

  • Hydrotest: 7/22/24 - 11/22/24
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Residents will see contractor trucks, water tanks, and heavy equipment. 24-hour work may be required on milestone dates.