Current Activities

Dates provided are estimates, weather and other factors affecting safe working conditions could change the schedules. The public may see trucks and heavy equipment from SoCalGas and our contractors around the general construction areas.

Beaumont

At Intersection of Highland Springs Ave and 1st St
  • Regulator Station Upgrade: 6/2/2025 – 11/2/2025
  • Work Hours: Monday – Friday from 7:00 am to 4:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Cabazon

On Elm St
  • Valve and Facility Upgrades: 4/7/2025 – 7/7/2025
  • Work Hours: Monday – Friday from 7:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas contractors.

Chino Hills

On Clubhouse Way
  • Validation Dig: 5/5/2025 – 6/16/2025
  • Work Hours: Monday – Friday from 7:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

City of Industry and Inglewood

At Puente Station in City of Industry and Crenshaw Station in Inglewood
  • In-line Inspection Equipment Setup: 4/14/2025 - 8/14/2025
  • Work Hours: Monday - Friday from 9:00 am to 3:30 pm (City of Industry); Monday - Friday from 8:00 am to 5:00 pm (Inglewood)
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and potential detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Colton

At the Colton Chevron
  • Natural Gas Vehicle Station Addition: 4/7/2025 – 6/7/2025
  • Work Hours: Monday – Friday from 7:00 am to 3:30 pm
  • Community Impacts: No parking and partial lane closure of the eastbound lane of E H St between N 10th St and N Mt. Vernon Ave. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Culver City

Northwest of intersection of W Centinela Ave and Arizona Ave
  • Validation Digs: 4/1/2025 – 7/1/2025
  • Work Hours: Monday – Friday from 8:00 am to 6:00 pm
  • Community Impacts: None.

Delano/Visalia

Delano Junction and Visalia Station
  • In-line Inspection: 3/31/2025 – 6/23/2025
  • Work Hours: Monday – Saturday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

El Monte

On Elliott Ave
  • Installation of Filter Seperator: 5/19/2025 – 6/23/2025
  • Work Hours: Monday – Friday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Glendora

  • Main and Service Line Replacements: 5/12/2025 – 8/12/2025
  • Work Hours: Monday - Friday from 7:00 am to 4:30 pm
  • Community Impacts: None. Occasional narrowing of traffic lanes near Tedrow Ave and Calmgrove Ave. Customers will see trucks and heavy equipment from SoCalGas and our contractors.
On Baseline Rd between Glendora Ave and Jenifer Ave
  • Main and Service Line Replacements: 6/23/25 - 8/23/2025
  • Work Hours: Monday - Friday from 7:00 am to 4:30 pm
  • Community Impacts: Traffic on Baseline Rd will see lane reductions in both directions of traffic. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Granada Hills

Near the intersection of Balboa Blvd and Lisette St
  • SCCDA Digs: 4/14/25 - 6/16/2025
  • Work Hours: Monday - Friday from 8:00 am to 4:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. The northbound bike lane on Balboa Blvd will be closed for approximately 250 feet around the construction area. The southbound two left lanes on Balboa Blvd will be closed for approximately 250 feet around the construction area. The northbound far-right lane on Balboa Blvd will be closed for approximately 250 feet around the construction area.

Handford

Multiple locations on Lacey Blvd
  • Hydrotest: 4/28/2025 - 9/8/2025
  • Work Hours: Monday - Thursday from 6:00 am to 5:30 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. Temporary crash cushion (19-barrel array system) with temporary railing located on the south-west corner on intersection of Lacey Blvd. and 7th Ave, East of the offramp from Hwy 198. Temporary crash cushion (19-barrel array system) with temporary railing located on south shoulder of Lacey Blvd heading East. Temporary crash cushion (19-barrel array system) with temporary railing located on southeast corner on intersection of Lacey Blvd. and 6th Ave.

Huntington Beach

Along Coral Cay and Bluewater
  • Main and Service Line Replacements: 6/23/2025 - 12/23/2025
  • Work Hours: Monday - Thursday from 8:00 am to 4:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Irvine

Between Marine Way and Barranca Pkwy 
  • Pipeline Relocation: 4/14/2025 - 8/14/2025
  • Work Hours: Monday - Thursday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. No traffic impacts are anticipated.

Jurupa Valley

At Intersection of Highland Springs Ave and 1st St
  • Validation Digs: 6/16/2025 - 9/16/2025
  • Work Hours: Monday - Friday from 9:00 am to 3:30 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Kern County

Wheeler Ridge Compressor Station to Edmonston Plant
  • In-line Inspection: 5/5/2025 - 6/30/2025
  • Work Hours: Monday - Saturday from 6:00 am to 6:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Los Angeles

Along Sepulveda Blvd near the intersection of Sepulveda Blvd and Valley Meadow Blvd
  • ECDA Indirect Assessment: 4/21/2025 - 8/11/2025
  • Work Hours: Monday - Friday from 8:00 am to 4:00 pm
  • Community Impacts: Traffic control signage, flagging personnel, no parking signage, and detours will be postponed along the construction route.

Ludlow/Newberry

From Ludlow to Newberry
  • Hydrotest: 5/27/2025 - 12/27/2025
  • Work Hours: Monday - Saturday from 6:00 am to 6:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas contractors.

Menifee

On Briggs Rd and Holland Rd
  • Drop Section: 4/7/2025 - 9/7/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Maricopa

  • Leak Repair: 5/19/2025 - 8/11/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. Single lane on Klipstein Canyon Road will be closed off 5/05/2025 to 08/05/2025. A section of Klipstein Canyon Rd will be closed off and not allow thru traffic on 6/04/25 - 6/06/2025 beginning at 6am for 24-48 hours. Traffic control will be used for the duration of the project.

Morongo Reservation

On Service Rd and Millard Pass Rd
  • Validation Digs: 5/12/2025 - 6/23/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Needles

At and around the South Needles Compressor Station
  • Remediation Digs: 4/28/2025 - 10/28/2025
  • Work Hours: Monday - Friday from 6:00 am to 4:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Newport Beach

In the 2 alleys between I St and L St, south of Balboa Blvd and north of Miramar Dr
  • New Main Installation: 3/31/2025 - 6/31/2025
  • Work Hours: Monday - Friday from 7:00 am to 3:00 pm
  • Community Impacts: Traffic control will be in effect for duration of the project. Alleyway access will be limited during work hours. Residents will see trucks and heavy equipment from SoCalGas and our contractors.
Near Intersection of University Dr and Jamboree Rd
  • Bypass Installation: 6/23/2025 - 8/23/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Oxnard

Intersection of Rice Ave and E. 5th St
  • Robo In-line Inspection/Direct Examination: 1/13/2025 - 6/13/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flagging personnel, no parking signage, lane closures, and detours will be posted along the construction route.

Palm Desert

Within Sliver Sands Raquet Club
  • Main and Service Line Replacements: 6/2/2025 - 10/2/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:30 pm; Saturday 8:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Rancho Cucamonga

Etiwanda Station
  • Robo In-line Inspection: 4/21/2025 - 7/21/2025
  • Work Hours: Monday - Thursday from 6:00 am to 5:00 pm
  • Community Impacts: Partial lane closures of westbound lanes of Arrow Rte. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Rancho Mission Viejo

Along Antonio Parkway, adjacent to Orange County Fire Station #56
  • Regulator Station upgrade: 5/19/2025 - 6/19/2025
  • Work Hours: Monday - Thursday from 9:00 am to 3:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. Traffic control will be in effect intermittently. 

Santa Ana

Along Red Hill Ave, south of Dyer Rd
  • CCM Work: 4/21/2025 - 6/21/2025
  • Work Hours: Monday - Thursday from 8:00 pm to 6:00 am
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. Traffic control will be in effect for the duration of the project. 
Along Grand Ave, between Dyer Rd
  • Validation Digs: 5/1/2025 - 7/1/2025
  • Work Hours: Monday - Friday from 7:00 pm to 7:00 am
  • Community Impacts: Traffic control will be in effect along Grand Ave area during work hours. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Santa Clarita/Castaic

Old Ridge Route Rd and Quigley Station
  • In-line Inspection: 6/9/2025 - 8/11/2025
  • Work Hours: Monday - Saturday from 6:00 am to 6:00 pm
  • Community Impacts: Traffic control signage, flagging personnel, no parking signage, and detours will be postponed along the construction route at the different location.

Santa Clarita/Saticoy

Launcher at 34°25’23.4”N118°34’18.5”W and Receiver at 34°16’21.4”N119°05’38.7”W
  • In-line Inspection: 6/9/2025 - 8/4/2025
  • Work Hours: Monday - Thursday from 7:00 am to 5:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors. In Santa Clarita, customers will see company vehicles along Magic Mountain Parkway. In Ventura, customers can anticipate traffic control measures and lane/road closures along Center Road and La Vista Avenue.

Santa Fe Springs

At Intersection of Orr and Day Rd and Joslin St
  • Main and Service Line Replacements: 6/16/2025 - 7/28/2025
  • Work Hours: Monday - Friday from 9:00 am to 4:00 pm
  • Community Impacts: Traffic control signage, flag personnel, lane closures, and detours will be posted along the construction routes. Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Santa Maria

Along California Blvd, between Flagstone Dr and Doverlee Dr
  • Remediation Dig: 6/30/2025 - 9/30/2025
  • Work Hours: TBD
  • Community Impacts: Traffic control signage, flagging personnel, no parking signs, and lane closures will be posted along the construction route.

Tehachapi

At - 35.0730317°, -118.6881393°
  • Main Replacement: 6/23/2025 - 8/4/2025
  • Work Hours: Monday - Friday from 6:00 am to 4:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.

Ventura

West of HWY 101 and HWY 1 off-ramp
  • Valve Repair: 5/19/2025 - 7/28/2025
  • Work Hours: Monday - Friday from 6:30 am to 5:00 pm
  • Community Impacts: None
Near the Intersection of N Olive St and W McFarlane Dr
  • Hydrotest: 6/9/2025 - 7/21/2025
  • Work Hours: Monday - Saturday from 6:30 am to 7:00 pm
  • Community Impacts: Customers will see trucks and heavy equipment from SoCalGas and our contractors.
Near the Intersection of W McFarlane Dr and N Ventura Ave
  • Leak Repair: 6/2025 - 8/2025
  • Work Hours: Monday - Friday from 7:00 am to 5:00 pm
  • Community Impacts: Traffic control signage, flagging personnel, no parking signs, and lane closures will be posted along the construction route.